B-229062:
Nov 13, 1987
A firm protested the Defense Logistics Agency's (DLA) rejection of its low bid for hydraulic ramps as nonresponsive, contending that DLA: (1) improperly required a bid bond, since the contract cost did not justify one; and (2) should waive its initial failure to submit a bid bond, since its late bid met the requirement. GAO held that: (1) DLA properly rejected the protester's bid, since it did not...