B-228232.2:
Feb 3, 1988
A firm protested the Army Corps of Engineers' denial of its preaward request to correct an alleged mistake in its low bid for the construction of a vehicle wash facility, contending that a subcontractor made an error which affected its bid price. GAO held that the: (1) requested correction would increase the bid to within 1 percent of the next low bid; and (2) protester failed to prove its alleged...