B-227811.2:
Nov 10, 1987
A firm requested reconsideration of its denied protest regarding the Bonneville Power Administration's (BPA) exclusion of it from competition for the construction of high voltage transmission lines. GAO had held that: (1) BPA regulations, not the Federal Acquisition Regulation, governed its procurement actions; and (2) the BPA prequalification panel reasonably determined that the protester lacked...