B-226774.4:
May 6, 1988
A firm requested reconsideration of its denied protest against the Coast Guard's rejection of its bid for maintenance services. GAO had held that the protester's bid was nonresponsive, since it had an insufficient bid guarantee at bid opening. In its request for reconsideration, the protester contended that its surety had a reinsurance policy to cover the additional amount required for the bid bon...