B-226531.2:
Jul 30, 1987
A firm protested the Air Force's cancellation of a solicitation for a computerized fire monitoring system, contending that the Air Force should have either: (1) awarded it the contract, since its bid was responsive and low; or (2) reimbursed it for its bid and protest preparation costs. GAO held that the Air Force properly cancelled the solicitation, since it: (1) did not receive any responsive bi...