B-226477:
Mar 17, 1987
A joint venture protested a proposed Navy construction contract award, contending that the Navy should have rejected the awardee's bid as nonresponsive, since the bid did not include a size-status certification. GAO held that: (1) the awardee's failure to certify its size did not affect its responsiveness, since the Navy did not need that information to determine whether the bid met the solicitati...