B-225709:
Apr 14, 1987
A firm protested an Army contract award for infrared filter assemblies, contending that the Army should have held discussions after it delayed the contract award. GAO held that the Army: (1) properly awarded the contract on the basis of initial offers, since the award resulted in the lowest overall cost to the government; (2) did not award the contract within the offer expiration date because of a...