[Request for Reconsideration of Denial of Protest Against Army Rejection of Bid]

B-224026.2: Apr 10, 1987

A firm requested reconsideration of the denial of its protest against an Army contract award for power pole replacement. GAO had held that the Army properly rejected the protester's bid as nonresponsive because, while the bid acknowledged a solicitation amendment, it did not include item prices for the items that the amendment added. In its request for reconsideration, the protester contended that...

  • pdf icon View Decision (PDF, 2 pages)
B-224026.2, APR 10, 1987, 87-1 CPD 394

B-224026.2: Apr 10, 1987

PROCUREMENT - BID PROTESTS - GAO PROCEDURES - GAO DECISIONS - RECONSIDERATION DIGEST: DECISION DENYING PROTEST OF BID REJECTION BECAUSE OF THE PROTESTER'S FAILURE TO SEPARATELY PRICE AN ITEM ADDED TO THE BID SCHEDULE BY AMENDMENT IS AFFIRMED WHERE THE PROTESTER HAS NOT SHOWN THE DECISION TO BE BASED ON ANY ERROR OF FACT OR LAW. WE UPHELD THE ARMY'S DETERMINATION THAT THE BID WAS NONRESPONSIVE FOR...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap