B-222681:
Jul 23, 1986
The Department of the Interior requested a review of a contractor's claim of a bid mistake, stating that before the award, the bidder alleged that it misunderstood a subcontractor's quotation for a portion of the work, but agreed to perform the contract at its bid price with the stipulation that the Comptroller General review the matter. GAO held that: (1) correction of a bid error was allowable p...