B-221889.2:
Jun 17, 1987
A firm requested a decision concerning its entitlement to reimbursement for bid and protest preparation costs pursuant to its sustained protest against the Navy's rejection of an amendment to its bid. GAO had held that Navy mishandling caused the late receipt of the amendment; therefore, it sustained the protest and recommended that the Navy terminate the contract and make award to the protester....