B-220693:
Nov 4, 1985
A firm protested an Air Force contract award for word processing systems, contending that the awardee should not have received the award since the product it proposed to supply did not meet certain performance specifications. The Air Force informed GAO that it had terminated the contract because it learned that the awardee quoted an open market price instead of the Federal Supply Schedule contract...