B-220626:
Jan 23, 1986
A firm protested an Army contract award for the installation of high temperature water lines, contending that its bid was improperly rejected as nonresponsive. The contracting officer determined that, at the time of bid opening, the liability of the protester's bond was uncertain because there was nothing to show that the principal representative signing the bid bond had authority to act on behalf...