B-220327:
Jan 29, 1986
A firm protested the rejection of its low bid under a Navy solicitation for torpedo shipping containers, contending that the Navy improperly rejected its bid. The Navy rejected the bid because the protester did not acknowledge a solicitation amendment or include a delivery schedule. GAO held that: (1) the amendment was not material because it had a negligible effect on price and was effectively a...