B-219356.2:
Jun 27, 1985
A firm requested reconsideration of a decision dismissing its protest as untimely. The protester originally protested the specifications of a procurement as unclear the day before bid opening, but despite its complaints, bid opening occurred as scheduled. In its request for reconsideration, the protester contended that it did not have knowledge of the adverse agency actions until it received notic...