The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Request for Reconsideration of Dismissal of Request for Reconsideration]

B-219312.5: Jan 9, 1986

An individual requested reconsideration of the dismissal of his request for reconsideration of the dismissal of his protest. The prior request for reconsideration was dismissed because it was not filed within 10 working days after the basis of the request was known. GAO found that the request was properly dismissed as untimely. Accordingly, the dismissal was affirmed...

  • pdf icon View Decision (PDF, 1 pages)
B-219312.5, JAN 9, 1986, 86-1 CPD 20

B-219312.5: Jan 9, 1986

CONTRACTS - PROTESTS - GENERAL ACCOUNTING OFFICE PROCEDURES - RECONSIDERATION REQUESTS - TIMELINESS DIGEST: REQUEST FOR RECONSIDERATION OF THE DISMISSAL OF A PROTEST WAS PROPERLY DISMISSED AS UNTIMELY WHERE IT WAS FILED MORE THAN 10 WORKING DAYS AFTER THE PROTESTER RECEIVED THE DISMISSAL OF THE PROTEST. WAS DISMISSED BECAUSE IT WAS NOT FILED AT GAO WITHIN 10 WORKING DAYS AFTER THE BASIS OF THE REQ...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap