B-218102.4:
Jul 24, 1985
A firm requested reconsideration of a GAO decision dismissing its protest of a Department of the Interior contract award, contending that GAO had erroneously concluded that the awardee's bid did not take exception to a contract requirement. GAO had dismissed the protest because it concerned contract administration, which GAO does not review, and also because it lacked evidence that the awardee's b...