B-216305:
Sep 24, 1984
A firm protested the evaluation of its bids under three Defense Logistics Agency (DLA) solicitations, contending that DLA improperly applied the Buy American act to the evaluation of the bids. GAO held that the protest was untimely filed because it was not received within 10 days of the time the protester knew the basis for the protest. Accordingly, the protest was dismissed...