B-215411.2:
Aug 20, 1984
A firm requested reconsideration of a decision in which GAO dismissed the firm's protest as untimely filed. The original protest was untimely because it alleged that the solicitation specifications were unduly restrictive and was not received by GAO until after the bid opening. The protester contended that the restrictive nature of the specifications did not become apparent until after the bid ope...