[Complaint That UMTA Grantee Improperly Rescinded Contract Award]

B-215309: Jun 27, 1984

A firm complained that an Urban Mass Transportation Administration grantee improperly rescinded a contract that it had awarded to the protester. GAO held that it would not consider the matter because the protester filed a lawsuit in a State court and the court did not express an interest in a GAO opinion. Accordingly, the protest was dismissed...

  • pdf icon View Decision (PDF, 2 pages)
B-215309, JUN 27, 1984

B-215309: Jun 27, 1984

DIGEST: WHEN MATERIAL ISSUES INVOLVED IN A COMPLAINT CONCERNING A PROCUREMENT BY A FEDERAL GRANTEE ARE ALSO BEFORE A STATE COURT. GAO WILL DISMISS THE COMPLAINT. THIS WAS DONE ON APRIL 11. WHICH REFUSED TO CONSIDER THE MATTER BECAUSE THE SAME ISSUES WERE INVOLVED IN NORSAIRE'S STATE COURT COMPLAINT. WE WILL NOT CONSIDER THE ALLEGEDLY IMPROPER RESCISSION OF THE CONTRACT (AND WE DO NOT HERE DECIDE T...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap