B-214250:
Feb 10, 1984
A firm protested any contract award under a solicitation issued by the Naval Sea Systems Command, contending that several of the terms in the solicitation were indefinite. GAO held that the protest was not received by GAO until 4 days after bid opening and was not timely filed. Accordingly, the protest was dismissed...