B-213526:
Nov 15, 1983
A firm protested the award of a contract to the low bidder under a Defense Logistics Agency solicitation for woven fabric, contending that the awardee was incapable of supplying the total amount of fabric required within the delivery schedule specified in the solicitation. A prospective contractor's capability of meeting a delivery schedule is a matter of responsibility, and GAO will not review af...