B-213224:
Oct 25, 1983
A firm protested that certain specifications in an invitation for bids issued by the Federal Emergency Management Agency were ambiguous and that no vendor could met the delivery schedule. GAO ruled that: (1) the protester's allegation concerning ambiguous specifications was untimely since it was not made prior to bid opening as required under bid protest procedures; and (2) the protester's complai...