The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Air Force Rejection of Bid]

B-213050: Sep 30, 1983

A firm protested the rejection by the Air Force of materials it proposed to supply as a subcontractor. The protester received an order from the prime contractor but the order was canceled because the Air Force had rejected the materials in question. The protester alleged that the Air Force specifications were "tremendously ambiguous," which GAO construed to mean that the specifications were so bro...

  • pdf icon View Decision (PDF, 2 pages)
B-213050, SEP 30, 1983

B-213050: Sep 30, 1983

DIGEST: PROTEST BY SUBCONTRACTOR OF AGENCY DECISION THAT MATERIALS TO BE SUPPLIED BY SUBCONTRACTOR UNDER PRIME CONTRACT ARE UNACCEPTABLE WILL NOT BE CONSIDERED UNDER GAO BID PROTEST PROCEDURES. SUBSEQUENTLY IT WAS INFORMED THAT THE PROPOSED MATERIALS WERE REJECTED BY THE AIR FORCE AND THAT PALMER WAS CANCELING ITS ORDER. LE PRIX OBJECTS TO THE AIR FORCE'S DECISION ON THE BASIS THAT THE SPECIFICATI...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap