B-213050:
Sep 30, 1983
A firm protested the rejection by the Air Force of materials it proposed to supply as a subcontractor. The protester received an order from the prime contractor but the order was canceled because the Air Force had rejected the materials in question. The protester alleged that the Air Force specifications were "tremendously ambiguous," which GAO construed to mean that the specifications were so bro...