B-212340.2:
Aug 9, 1983
A firm requested reconsideration of a decision which dismissed as untimely a protest alleging that a solicitation requirement was unreasonable. In its request for reconsideration, the protester asked for the opportunity to modify its bid to include the required item. However, GAO held that a bid which is nonresponsive initially may not be corrected after bid opening. Further, since the protester w...