B-212229:
Jan 19, 1984
A firm protested an Air Force contract award under a request for proposals (RFP) for the operation and maintenance of aerial target systems. The protester claimed that, because it submitted the lowest price offer and its technical proposal was rated "good," it was entitled to the award. GAO noted that, not only did the RFP state that technical and cost proposals would be evaluated equally, but tha...