The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Cancellation of Solicitation]

B-210775: Aug 9, 1983

A firm protested that the Army improperly canceled an invitation for bids (IFB) for truck parts without a cogent and compelling reason and contended that it should have been awarded the contract because it was the lowest responsive, responsible bidder. The Army canceled the IFB because an amendment, which had been added to the solicitation in response to the protester's suggestion, was not issued...

  • pdf icon View Decision (PDF, 3 pages)
B-210775, AUG 9, 1983

B-210775: Aug 9, 1983

THE IFB WAS ISSUED ON NOVEMBER 29. MOTT HAVEN CONTENDS THAT IT SHOULD HAVE BEEN AWARDED THE CONTRACT BECAUSE IT WAS THE LOWEST RESPONSIVE RESPONSIBLE BIDDER THAT ACKNOWLEDGED THE AMENDMENT. BECAUSE THE AMENDMENT WAS NOT ISSUED IN SUFFICIENT TIME TO PERMIT ALL THE PROSPECTIVE BIDDERS TO CONSIDER THE INFORMATION BEFORE SUBMITTING THEIR BIDS. WE HAVE HELD THAT THE AUTHORITY OF A CONTRACTING OFFICER T...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap