B-209707:
Apr 22, 1983
A firm protested the rejection of its bid as nonresponsive under a solicitation issued by the Army Corps of Engineers for the construction of a comfort station. The original solicitation contained 17 separate items and instructed bidders that they were required to bid on all items. Prior to bid opening, the Army issued an amendment which changed a number of specifications and revised the schedule...