B-208757.2:
Jun 8, 1983
A firm protested the rejection of its bid by a naval supply center alleging that it should not have been ruled ineligible under the Walsh-Healey Act. GAO stated that it does not consider the legal status of firms under the act, since this is a matter of contract administration. GAO also stated that it is limited to considering whether the contracting officer complied with procedural requirements....