B-208290:
Sep 7, 1982
A firm submitted a claim under the Meritorious Claims Act for payment for a radar range calibrator which had been delivered to the Navy under a contract which called for 634 calibrators, all of which were delivered. The Navy withheld payment for the last unit shipped pending a decision on what action should be taken because of alleged contract violations. The Navy dropped the question of contract...