B-208134:
Dec 7, 1982
A firm protested the rejection of its bid under an invitation for bids (IFB) issued by the National Aeronautics and Space Administration (NASA) and the award of the contract to the second low bidder. The question concerned whether the protester made an error in its low bid. NASA stated that the IFB required the contractor to construct an uninterruptible power supply system and four power centers a...