The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Request for Reconsideration]

B-207682.2: Mar 30, 1983

A firm requested reconsideration of a decision which denied its protest of a Department of Energy (DOE) contract award for construction and demolition work. In the prior decision, GAO held that DOE reasonably permitted the awardee to correct a bid error. In its request for reconsideration, the protester alleged that the awardee was a large business, thus precluding it from the contract award. GAO...

  • pdf icon View Decision (PDF, 4 pages)
B-207682.2, MAR 30, 1983

B-207682.2: Mar 30, 1983

REQUEST FOR RECONSIDERATION OF PRIOR DECISION IS DENIED WHERE PROTESTER HAS NOT SHOWN THAT ITS CONCLUSION - THAT CONTRACTING OFFICER PROPERLY PERMITTED LOW BIDDER TO CORRECT A MISTAKE-IN-BID - RESULTED FROM AN ERROR OF LAW OR FACT. 2. COLEMAN DOES NOT MENTION THE MISTAKE- IN-BID ISSUE WHICH WAS THE SUBJECT OF OUR PRIOR DECISION. COLEMAN STATES THAT IT HAS REASON TO BELIEVE THAT WOMACK IS A LARGE B...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap