B-206555:
Aug 18, 1982
A firm protested the rejection of its bid under an invitation for bids issued by the Corps of Engineers. The bid was rejected because it did not include a bid bond with its bid. Instead, the protester attached to its bid bond form a pledge and assignment of collateral of all amounts which were due and payable or held as retainage under three ongoing Government contracts. The protester contended th...