The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Cost-Plus-Fixed-Fee Contract Award]

B-204969: Aug 18, 1982

A firm protested the award of a cost-plus-fixed-fee contract for maintenance of an automated systems database. The agency found the protester's technical proposal to be technically unacceptable and ruled that the awardee's was reasonable and realistic. The protester argued that: (1) the proposal technical evaluation was defective in the scoring of both its proposal and the awardee's proposal; (2)...

  • pdf icon View Decision (PDF, 6 pages)
B-204969, AUG 18, 1982

B-204969: Aug 18, 1982

PROTEST OF TECHNICAL EVALUATION OF PROPOSAL IS DENIED WHERE PROTESTER HAS NOT SHOWN EVALUATION TO BE UNREASONABLE OR ARBITRARY. 2. PROPOSAL OF MORE THAN ESTIMATED NUMBER OF MAN-YEARS IN RFP IS NOT A DEPARTURE FROM RFP REQUIREMENTS. SINCE ESTIMATE WAS MERELY THAT AND NOT A REQUIREMENT. DDC ESSENTIALLY ARGUES THAT THE TECHNICAL EVALUATION WAS DEFECTIVE. QUESTIONS ASKED BY PROSPECTIVE OFFERORS WERE A...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap