B-203798:
Jul 24, 1981
A firm protested the award of a subcontract pursuant to an Army contract for the construction of a Government-owned, contractor-operated facility. About 2 weeks prior to the date for submission of best and final offers, the prime contractor amended the request for proposals (RFP) specifications. The protester asserted that the prime contractor requested that the Army waive the lower noise level ra...