B-203579:
Jun 29, 1981
A firm protested the General Services Administration (GSA) cancellation and follow-on resolicitation of a construction project. Under the first procurement, the protester submitted the only offer. However, GSA rejected the bid on the ground that its price was excessive. The procurement was subsequently resolicited. A protest by the firm to GSA was received 5 hours after bid opening. Since the firm...