B-197445:
Mar 11, 1980
A firm protested the rejection of its bid for failure to submit an adequate bid guarantee. Subsequently, the protester sought permanent injunctive relief in the U.S. District Court, thereby placing the material issues involved in the protest before the court. The GAO policy is not to decide protests where the material issues are before a court of competent jurisdiction unless the court requests, e...