Subcontractor's Claim for Final Payment From Prime Contractor

B-193145 Oct 30, 1978
Jump To:
Skip to Highlights

Highlights

New Windsor Metal Fabrications, Ltd. (New Windsor), a subcontractor on the Army Corps of Engineers Technical Data Facility project at Picatinny Arsenal, alleges that as of September 26, 1978 it has not received final payment from the prime contractor. Under the Miller Act, New Windsor has the statutory right to sue on the payment bond furnished to the United States by the prime contractor; the right to sue is limited to one year.