Untimely Protest against Award of Certain Contract Items

B-192042: Aug 31, 1978

A company protested award of certain contract items and contended that it did not receive an amendment correcting discrepancies in the bid schedule. The protest was filed more than 10 days after the company's knowledge of adverse agency action and was untimely. While the protester may have been unaware of Bid Protest Procedures and their time constraints, the procedures have been published in the...

  • pdf icon View Decision (PDF, 3 pages)
B-192042, AUG 31, 1978

B-192042: Aug 31, 1978

DIGEST: PROTEST FILED WITH GAO MORE THAN 10 WORKING DAYS AFTER ACTUAL KNOWLEDGE OF INITIAL ADVERSE AGENCY ACTION IS UNTIMELY AND NOT FOR CONSIDERATION. WHILE PROTESTER MAY HAVE BEEN UNAWARE OF PROTEST PROCEDURES. PROCEDURES ARE PUBLISHED IN FEDERAL REGISTER AND PROTESTER IS CHARGED WITH CONSTRUCTIVE NOTICE THEREOF. INDICATING WHAT ACTIONS IT HAD TAKEN TO INSURE THAT THE ISSUANCE OF THE AMENDMENT W...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap