Failure To Meet Solicitation's Bid Acceptance Period

B-191390 Jul 26, 1978
Jump To:
Skip to Highlights

Highlights

A company requested reconsideration of a decision denying its protest against rejection of its bid because it did not provide for the same bid acceptance period as did the solicitation. Even though the agency could make the award in less time, the bidder's failure to offer the specified period rendered the bid nonresponsive.