B-190658:
May 16, 1978
A protester complained that it was excluded from competition by a grantee because of unduly restrictive procurement requirements. The complaint was sustained because the: (1) grantee's procurement practices were inconsistent with the requirement that needs should be filled competitively; (2) grantee did not determine that its requirements could not be filled with a two-cycle design which it did no...