Skip to main content

Allegations by Contractor That Its Contract Should Have Been Extended

B-190310 Jan 23, 1978
Jump To:
Skip to Highlights

Highlights

An incumbent contractor protested against the method of contracting used during an interim period between expiration of the contract and award of a new contract, arguing that the agency should have extended its contract. Since the old contract had no option to extend, the only way to extend the contract was by sole-source negotiation which was not justified.