Skip to main content

Negotiated Contract Was Justified by Public Exigency

B-190246 Jun 26, 1978
Jump To:
Skip to Highlights

Highlights

A carrier protested the award of a contract through negotiation, contending that no public exigency existed, that it was not solicited, and that it could have peformed the services at lower cost. The agency's determination to negotiate the contract was not questioned since time factors were critical and did not permit advertising.