Carrier's Failure To Hold Operating Authority Makes Him Ineligible for Award
B-190091
Feb 14, 1978
Skip to Highlights
Highlights
A common carrier who was the low offerer on a solicitation but did not hold an operating authority from the Interstate Commerce Commission proposed that the contracting officer have a substitute carrier sign the contract and assume responsibility or seek an emergency temporary operating authority for itself. Failure to have the operating authority which was a solicitation requirement made the offerer ineligible for award. A negotiated contract may not be awarded to a party which did not submit a timely proposal in the absence of a corporate acquisition, sale of an entire business, or transfer of the portion of the business embraced by the contract.
Downloads
GAO Contacts
Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel