B-188678:
Jun 7, 1977
PROTEST TO GAO ALLEGING IMPROPER REJECTION OF BID AS NONRESPONSIVE WILL NOT BE CONSIDERED SINCE DISMISSAL OF CASE BY UNITED STATES DISTRICT COURT HAD EFFECT OF FINAL ADJUDICATION ON MERITS ON RELIEF SOUGHT. BRISK'S BID WAS DETERMINED TO BE NONRESPONSIVE FOR FAILURE TO LIST PROPOSED SUBCONTRACTORS FOR CERTAIN SPECIFIED AREAS OF WORK TO BE PERFORMED UNDER THE CONTRACT AS REQUIRED BY THE SOLICITATION...