Request for Contract Modification Due to Mistake in Bid Alleged before Awarding of Contract Is Denied

B-187023 Oct 18, 1976
Jump To:
Skip to Highlights

Highlights

Professional Electronics Company requested an increase in its contract for a transmitter at the U.S. Army Yuma Proving Ground. Although a mistake in calculation was admitted, the request for contract modification was denied because the information did not clearly indicate what the intended bid should have been.