Request for Contract Modification Due to Mistake in Bid Alleged before Awarding of Contract Is Denied
B-187023
Oct 18, 1976
Skip to Highlights
Highlights
Professional Electronics Company requested an increase in its contract for a transmitter at the U.S. Army Yuma Proving Ground. Although a mistake in calculation was admitted, the request for contract modification was denied because the information did not clearly indicate what the intended bid should have been.
Downloads
GAO Contacts
Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel