Available Funding Increases After Bid Opening and Prior to Award

B-186961 Nov 09, 1976
Jump To:
Skip to Highlights

Highlights

A company protested the award of a contract for surfacing missile base roads, arguing that the award should have been made within the limits of available funds. If the available funding increases prior to bid award, the agency may properly rely on the additional funds in making the award.