Protest against Evaluation Plan and Agency's Failure to Communicate Reduced Requirements

B-18639: Jun 27, 1977

Additional Materials:


Office of Public Affairs
(202) 512-4800

Company's eight point protest was basically that agency failed to communicate to them a change in requirements, which made its proposal much higher than competitor's. Company further alleged that its prices were competitive on a staff-day basis. Moreover, request for proposals indicated evaluation would be based on technical/cost relationship, rather than cost alone. Award was improper, but it is impractical to cancel. Protest against responsibility will not be considered. Several other issues were untimely. (DJM)

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.