Untimely Protest Against Procurement Procedures

B-185688: Jan 30, 1976

A company protested against any contract award under a solicitation after its protests with the agency against alleged procedural errors was denied. The protest to GAO was untimely since it was filed more than 10 days after the protester's receipt of notification of adverse agency action...

  • pdf icon View Decision (PDF, 2 pages)
B-185688, JAN 30, 1976

B-185688: Jan 30, 1976

PROTEST TO GAO OF AWARD UNDER REQUEST FOR PROPOSALS IS UNTIMELY WHERE FILED MORE THAN 10 WORKING DAYS AFTER PROTESTER'S RECEIPT OF NOTIFICATION OF ADVERSE AGENCY ACTION ON PROTEST TO AGENCY. ADR PROTESTED THAT ITS COMPETITIVE POSITION WAS WEAKENED FOLLOWING THE OCTOBER 2 NEGOTIATION SESSION BECAUSE OF INFORMATION IT REVEALED TO ANOTHER OFFEROR AS A RESULT OF ITS INTERPRETATION OF CERTAIN STATEMENT...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap