B-185003:
Jan 2, 1976
A contractor requested a review of a settlement which disallowed its claim for an amount representing the sum withheld from its contract invoice to cover costs incurred by the agency for repair of a defective transformer. The claim was improperly forwarded to, and considered by, the Transportation and Claims Division. Since the matter was for processing under the disputes clause of the contract, i...