Determination That Low Bid Could Be Corrected

B-184332 Jun 07, 1976
Jump To:
Skip to Highlights

Highlights

The protester objected to the contracting officer's determination that the low bidder could modify its bid. The administrative determination to allow correction was not disturbed since the mistake was alleged prior to award, and the bidder presented clear and convincing evidence of the nature and existence of the mistake and of the bid actually intended, and the corrected bid did not displace any other bidder. The contention that the corrected bid should be calculated on the basis of costs contemplated by other bidders was without merit.